Independent IFS Cloud practice · Order promising design
Decide what the master schedule promises before customer orders depend on it
Master Scheduling Available to Promise (ATP) is a promising method in IFS Cloud that uses the master schedule (MPS) as the data source for customer order promising. A promise date from this method is only as sound as the set-up behind it: which parts are master scheduled, whether online consumption is enabled, and whether quantities are allocated to customers or markets. If nobody chose these settings, the dates given to customers do not follow from a plan the business understands. This article follows the IFS documentation page on Master Scheduling Available to Promise, which has identical text in the 25R2 and 26R1 trees.
Key takeaways
- The method uses the master schedule (MPS) as data source for customer order promising, so the parts must be master scheduled, and Online Consumption on Inventory Part must be enabled.
- The page describes a generic check of whether the part is available at all on a certain date, and an additional check against the quantity allocated to an entity of a customer dimension.
- A customer dimension can be customer, customer stat group, market, region, district or country, and the period can be week or month.
- The page names five settings: Promise Method, Forecast By, Unallocated Supply Distribution, ATP Allocation Period Unit and ATP Allocation Method.
- With the method Available to Promise, a customer order line can only be entered or changed if total supply exceeds the demand quantity; a wanted receipt date inside the planning time fence gives an error message.
- The documentation does not recommend using more than one order promising tool for the same part at the same time.
1.What is Available to Promise in IFS Cloud, and where does it get its data?
Available to Promise uses the master schedule (MPS) as data source for customer order promising, hence the parts must be master scheduled.
The page describes two principles for the availability evaluation. One works against unconsumed forecast. The other, against unconsumed supply, looks at actual existing supplies and at how much of them can be promised after existing demands have been deducted. The page adds that within the planning time fence there can be a significant difference to unconsumed forecast.
The page lists three order promising tools: Availability Check, Capability Check and Available to Promise. It is not recommended to use more than one order promising tool for the same part at the same time. Order promising from the plan is covered in high-fidelity discrete order promising in IFS Cloud, and capable-to-promise in CTP in IFS Cloud.
2.What must be enabled for it to work?
To use this promising method, Online Consumption on Inventory Part must also be enabled. The page lists the events that count in online consumption:
- When you enter a new line.
- When you increase the quantity of an existing line.
- When you change any data on an existing line that affects the due date.
- When you decrease the quantity for an existing line.
- When you cancel an existing line.
For sales quotation lines, the Release for Planning option must be enabled on the sales quotation line.
3.What is the difference between the generic check and the customer-dimension check?
The generic check tests whether the part is available at all on a certain date. In addition to it, another check can be performed to see whether the part is available according to the allocated quantity for an entity of a customer dimension.
A customer dimension could be customer, customer stat group, market, region, district or country. The period could be week or month. The business decides for each part whether it is promised against the generic check only or also against an allocation, and for which dimension and period.
4.Which settings steer the check?
The page names the settings in the table below, with the definition or condition it gives for each and its possible values.
| Setting | What the page says | Values |
|---|---|---|
| Promise Method | Defines if available quantity is evaluated against unconsumed supply or unconsumed forecast | Unconsumed Forecast; Available to Promise (Unconsumed Supply) |
| Forecast By | Defines if ATP should also cover customer dimension based availability and which dimension is used for aggregation per time period | Part, Customer, Customer Stat Group, Region, Market, District, Country |
| Unallocated Supply Distribution | When Forecast By is not Part, controls how the allocation of non-specifically defined customer dimensions will be allowed to use | Free, Restricted |
| ATP Allocation Period Unit | The period unit of the allocation | Month, Week |
| ATP Allocation Method | Method of the allocation | First Come First Served, Forecast Ratio, User Defined Ratio, Fixed Quantity Limit |
The settings list of the page says Promise Method, and a later passage says Promised Method in the MS Level 1 Part page. Treat both as the same setting and check the label in your release.
5.What happens on a customer order line?
With the promise method Available to Promise, you can only enter or change a Customer Order or Quotation Line if the sum of the stock on hand plus open supply, that is the total supply, exceeds the demand quantity. The condition applies to that method only, and the page ties it to the planning time fence (PTF).
The two methods behave as follows relative to the PTF and the demand time fence (DTF), in the words of the page.
| Promise method | Planning time fence (PTF) | Demand time fence (DTF) |
|---|---|---|
| Available to Promise | Wanted receipt date inside the PTF: error message. Beyond the PTF: an information message, and the record can be saved | You are not restricted by the DTF |
| Unconsumed Forecast | The check goes for the entire horizon, also outside the PTF | You are restricted by the DTF |
6.How do time fences relate to lead time?
The planning time fence represents the cumulative lead time of the part, that is, the length of time it would take to produce the part if none of the subassemblies were in stock. The demand time fence is the shorter of the two periods, and a demand time fence of 0 means that no demand time fence applies.
The IFS page on time fences states that the planning time fence is calculated with the critical path method, and that the values are calculated using the manufacturing calendar for manufactured parts and the distribution calendar for purchased parts. The lead time definitions behind a promise date are covered in lead times in IFS Cloud for purchased and manufactured parts, and the planning run that feeds the schedule in dynamic structures and MRP.
7.Which decisions belong to planning and sales?
Three decisions need a named owner. Planning decides which parts are master scheduled and which single promising tool each part uses. Planning and sales together decide whether a part is promised against the generic check only or also against an allocation, and for which customer dimension and period. Sales decides what a customer service agent does when the system returns an error or an information message on a line. The order flow that surrounds the promise is described in customer order types in IFS Cloud. Reservation of stock for the line is a separate mechanism with its own rules, described in reservation rules in IFS Cloud.
8.How do you test promising before go-live?
Test promising with scenarios that cover each condition the page names, and write down the expected result before each one.
| Scenario | Expected result | Owner |
|---|---|---|
| Part that is not master scheduled | Record the result; the page requires master scheduled parts | Planner |
| Online Consumption disabled on the inventory part | Record the result; the page requires it for this method | Planner |
| Available to Promise, wanted receipt date inside the PTF, total supply not above demand | Error message | Sales |
| Available to Promise, wanted receipt date beyond the PTF | Information message; the record can be saved | Sales |
| Unconsumed Forecast, line inside the DTF | Restricted by the DTF | Sales |
| Forecast By set to a customer dimension, one entity | Availability is evaluated against the quantity allocated to that entity | Planner and sales |
| Increase, decrease and cancel an existing line | Each event is listed on the page as online consumption; record the consumed quantity before and after | Planner |
9.What does a promising set-up checklist contain?
The promising set-up is ready for go-live when each check below has a record behind it.
- The parts promised with ATP are master scheduled, and the list is written down.
- Online Consumption on Inventory Part is enabled for each of them.
- Promise Method and Forecast By are decided per part.
- Where Forecast By is not Part, Unallocated Supply Distribution is decided.
- Where quantities are allocated, the period unit and the allocation method are decided.
- Each part has one order promising tool.
- Sales quotation lines that must be promised have Release for Planning enabled.
- The seven test scenarios are recorded with evidence.
10.Frequently asked questions
What is Available to Promise in IFS Cloud?
Available to Promise in IFS Cloud Master Scheduling is a promising method that uses the master schedule (MPS) as data source for customer order promising. Online Consumption on Inventory Part must be enabled to use it.
Which parts can be promised with ATP?
Only master scheduled parts can be promised with Available to Promise in IFS Cloud, because the method uses the master schedule (MPS) as data source. The documentation does not recommend using more than one order promising tool for the same part at the same time.
What is the difference between the generic check and the customer-dimension check?
The generic check in IFS Cloud Available to Promise tests whether a part is available at all on a certain date. The customer-dimension check is an additional test of whether the part is available according to the allocated quantity for an entity of a customer dimension, for example one customer or one market.
Which customer dimensions can an ATP allocation use?
An ATP allocation in IFS Cloud can use customer, customer stat group, market, region, district or country as customer dimension, and the period can be week or month. The dimension is selected with the Forecast By setting, whose values are Part, Customer, Customer Stat Group, Region, Market, District and Country.
What must be enabled on the inventory part for ATP?
Online Consumption on Inventory Part must be enabled to use Available to Promise in IFS Cloud. Online consumption is triggered by entering a new line, increasing or decreasing the quantity of an existing line, changing data that affects the due date, and cancelling a line.
11.About the author
Dariusz Myśliwiec: 18 years hands-on with IFS, including IFS Cloud. Based in Kraków, delivering remotely across Europe and globally through an independent practice. You talk to the consultant who does the work, not a sales layer.
IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.
Do your promise dates follow from a plan you can explain?
A review of the promising set-up against your planning method shows which settings were chosen and which were left as they came.