IFS Cloud Routing Lead Time: Fixed, Variable and Overlap

Independent IFS Cloud practice · Manufacturing planning design Check your routing data against the calculation that produces the planned lead time IFS Cloud routing lead time is the lead time of a manufactured part calculated from its routing, and the page states that MRP and Master Scheduling use it. If the…

Read more

IFS Cloud Email Customer Documents: Set-Up Rules

Independent IFS Cloud practice · Sales output design Check the contact, the document and the event before customers say they never got the invoice To make IFS Cloud email customer documents reach customers, each document needs its own set-up: an invoice, a quotation and an order confirmation each have their own page…

Read more

IFS Cloud Lead Time: Purchase, Manufacturing and Expected

Independent IFS Cloud practice · Planning data design Know which lead time a function reads before you fill the fields IFS Cloud lead time lives in several fields, and each field has its own meaning. If purchase, manufacturing and expected lead time are filled without knowing which one a function reads, planned dates…

Read more

IFS Cloud Multi-Supplier Ordering: How Splits Work

Independent IFS Cloud practice · Purchasing design Split a requirement between suppliers on purpose, and check the quantities before the orders go out IFS Cloud multi-supplier ordering divides the quantity of one purchase requisition between suppliers by percentage. One supplier cannot or should not carry the whole…

Read more

IFS Cloud Email Purchase Orders: Event Set-Up

Independent IFS Cloud practice · Purchasing output design Make the purchase order reach the supplier: the event, the action and the condition To make IFS Cloud email purchase orders reach suppliers, the PDF_REPORT_CREATED event has to be enabled and an action of type E-Mail has to exist for it. The IFS documentation…

Read more

IFS Cloud Warehouse Data Collection: Design for the Floor

Independent IFS Cloud practice · Warehouse floor design Move the transaction to the point of work, one tested process at a time IFS Cloud Warehouse Data Collection is the documentation area for executing warehouse transactions through a scanning page, so that the transaction is entered where the work happens. Without…

Read more

IFS Cloud Sourcing Rules: How an Order Finds Its Supply

Independent IFS Cloud practice · Order supply design Decide where an order gets its supply before the system decides for you IFS Cloud sourcing rules describe where supply for an order line may come from and how the system chooses between the alternatives. An order line needs supply, and the source is picked by a rule…

Read more

IFS Cloud Document Attachments: Set the Convention Early

Independent IFS Cloud practice · Document handling design Set the attachment convention before the first file is added IFS Cloud document attachments are easy to add, and nobody has to agree a convention first. The system then fills with files named by habit, linked to the wrong object and held in revisions nobody can…

Read more

IFS Cloud Background Jobs: Design for the Night They Fail

Independent IFS Cloud practice · Operations design IFS Cloud background jobs: know every morning what ran last night IFS Cloud background jobs are tasks the system runs outside a user’s session: planning runs, postings, clean-ups and integration work. They are built once, pass in test, and are then forgotten, until a…

Read more

Independent IFS Cloud practice · Manufacturing planning design

Check your routing data against the calculation that produces the planned lead time

IFS Cloud routing lead time is the lead time of a manufactured part calculated from its routing, and the page states that MRP and Master Scheduling use it. If the calculation is not understood, routing data is maintained without knowing how setup, transport, queue, run time, lot size and overlap enter the total. Planned dates for manufactured parts then follow from data nobody checked against the calculation. This article follows the 26R1 page on the routing lead time calculation. The three lead time types and the purchase side are covered in IFS Cloud lead time: purchase, manufacturing and expected.

Key takeaways

  • The calculation can be based on machine time, labor time or the maximum of machine and labor time, and it can be run for current and future revisions and for all routing alternates of a part.
  • For a routing alternate with no parallel or overlapping operations, fixed lead time is the sum of setup, transport and queue time for all operations, and variable lead time is the sum of machine or labor time for all operations.
  • The lot size is normally the standard lot size on the inventory part; an operation quantity factor changes it for an operation.
  • For parallel operations only the operation that takes the longest is considered.
  • Overlap is defined on the routing operation as a percentage or as a number of units; the page that describes it belongs to scheduling, and the routing page states that the lead time formula does not cover calculations for operations with overlap.
  • The worked example table has three examples from the page: without overlap 27h, with overlap in units 17h and with overlap in percent 17h.

1.What does the routing lead time calculation produce, and who uses it?

The calculation produces a lead time for a manufactured part, and the page states that routing lead time is used in several places, among them MRP and Master Scheduling. The MRP page adds that for a manufactured or remanufactured part MRP calculates the lead time for a supply based on the valid routing.

Routing lead time calculations can be based on machine time, labor time or the maximum of machine and labor time. The calculation considers setup, transport and operation times, efficiency factor, overlap and eventually also the operation quantity factor entered for the operations. It also considers the information about queue time and shifts, such as the number of work hours per day, from the work center. The result can be calculated for the current and future revisions and for all routing alternates for a part, and optionally the inventory part can be updated with the lead time calculated for the default routing alternate and the current revision.

The capacity basis is a further choice. The page explains that the average capacity represents the projected usage based on the current work center parameters, and the demonstrated capacity represents the past actual usage. The planning side is covered in dynamic structures in MRP.

2.What counts as fixed time and what as variable time?

Fixed time does not depend on the lot size, and variable time is time per unit. The page states the sums for a routing alternate having no parallel or overlapping operations: the fixed lead time is the sum of setup time, transport time and queue time for all operations, and the variable lead time is the sum of machine or labor time for all operations.

Queue time is added as fixed time. The page notes that in its examples the work centers are assumed to have no queue time, and that if queue time had been defined, that time would be added as a fixed lead time. The calculation takes the queue time and the shifts from the work center, so that data belongs in the review.

3.Which lot size does the calculation use?

The lot size is normally the standard lot size specified on the inventory part. If an Operation Qty Factor is defined for an operation, that percentage of the standard lot size is used for it.

The page also says it is possible to simulate lead time for other lot sizes using Calculate Lead Time from the Routing, Routing Alternate or Routing Alternates pages. A simulation is the way to see what a different lot size does to the total before anyone changes the standard lot size of the part.

4.How are parallel operations treated?

For parallel operations only the operation that takes the longest to complete is considered when calculating the fixed and variable lead time. A shorter operation that runs in parallel therefore adds nothing to the total, and changing its time has no effect unless it becomes the longest.

5.How does overlap change the total?

Overlap lets a succeeding operation start before the preceding operation has finished, and it is defined on the routing operation. The page on operation overlap belongs to scheduling and not to the lead time calculation. It states that the overlap time can be defined either as a percentage of the preceding operation’s scheduled manufacturing lead time or as a number of units. It also states that if the part routing has operation overlap defined, the lead time calculation will accommodate the overlap times and the calculated lead time value will be reduced.

The two pages state limits that matter for data maintenance:

  • For an operation that overlaps with the previous operation, the contribution depends on the overlap and on the difference in run time between the operations.
  • It will not be possible to finish the succeeding operation before the preceding operation’s scheduled end time plus transportation time plus the time it takes the succeeding operation to manufacture the last delivered overlap quantity.
  • If an overlap time is defined on the first operation in an operation structure, with no defined preceding operation, it has no effect.
  • Operations defined as parallel simply overwrite the overlap functionality.

The routing page is explicit that the formula does not cover calculations for operations with overlap, so the fixed and variable sums of section 2 hold only for routings without overlap. The overlap information is transferred automatically to the order operation when an order operation is created from a routing revision, and it can be modified there.

6.What do the worked examples on the page show?

The page works examples with a lot of 5 pieces, and three of them show how the total follows from the inputs.

Example Fixed lead time Variable lead time Total
No overlap 7h 4h 7h + (4h * 5 pcs) = 27h
Overlap in units 7h 2h 7h + (2h * 5 pcs) = 17h
Overlap in percent 5h 2.4h 5h + (2.4h * 5 pcs) = 17h

The page also contains an example whose stated fixed time and calculated total do not agree with each other, and this article does not use it. Where a page example and its formula disagree, test the routing in your own system and compare.

7.What does the routing figure assume about components?

The routing figure assumes that all parts are available from inventory. When components can be missing, the expected lead time field is the one the documentation points to, as described in the lead time article. Order promising is covered in high-fidelity discrete order promising and, for capable-to-promise, in CTP in IFS Cloud.

8.Which decisions belong to manufacturing engineering and planning?

Manufacturing engineering owns the routing times, the overlap definitions and the work center queue time, and planning owns the standard lot size and the choice between average and demonstrated capacity. Agree who changes each value and how often it is reviewed. A related argument about static manufacturing set-up is made in the architectural failure of static manufacturing.

9.How do you test routing lead time before go-live?

Test routing lead time with one routing per case, calculate the expected total by hand from the page’s rules, and compare it with the system’s result.

Case Expected total Owner
Routing without overlap or parallel operations Fixed sum plus variable sum times the standard lot size Manufacturing engineer
Routing with a work center that has queue time The queue time is added as fixed lead time Manufacturing engineer
Routing with parallel operations Only the longest parallel operation counts Manufacturing engineer
Routing with overlap A reduced total, which the formula does not cover; compare with the system and record the difference Planner
Other lot size A simulation with Calculate Lead Time for that lot size Planner

10.What does a routing data checklist contain?

Routing data is ready for go-live when each of the checks below has a record behind it.

  1. Setup, transport and run times are entered for every operation.
  2. Queue time is defined on the work centers and its source is known.
  3. The standard lot size is set on the inventory part, and any operation quantity factor is intended.
  4. Parallel operations are marked and the longest one is the one that should count.
  5. Overlap is defined as a percentage or in units, and operations defined as parallel do not also carry overlap.
  6. The capacity basis, average or demonstrated, is decided.
  7. The five test cases are recorded with evidence.
  8. Each value has an owner and a review date.

11.Frequently asked questions

How does IFS Cloud calculate routing lead time?

IFS Cloud calculates routing lead time from the routing, based on machine time, labor time or the maximum of the two. It considers setup, transport and operation times, efficiency factor, overlap, the operation quantity factor, queue time and the shifts of the work center. The result is used by MRP and Master Scheduling.

What is the difference between fixed and variable lead time?

For a routing alternate with no parallel or overlapping operations, fixed lead time in IFS Cloud is the sum of setup time, transport time and queue time for all operations, and variable lead time is the sum of machine or labor time for all operations. The total is the fixed lead time plus the variable lead time multiplied by the lot size.

Which lot size does the routing lead time calculation use?

The lot size is normally the standard lot size specified on the inventory part. If an Operation Qty Factor is defined, that percentage of the standard lot size is used. Other lot sizes can be simulated with Calculate Lead Time from the Routing, Routing Alternate or Routing Alternates pages.

How are parallel operations counted?

For parallel operations, IFS Cloud considers only the operation that takes the longest to complete when it calculates the fixed and variable lead time. Operations defined as parallel also overwrite the overlap functionality.

What does overlap do to the total?

If the routing has operation overlap defined, the lead time calculation in IFS Cloud accommodates the overlap times and the calculated lead time is reduced. Overlap is defined on the routing operation as a percentage or a number of units. The routing page states that its formula does not cover calculations for operations with overlap, so verify overlapped routings against the system.

12.About the author

Dariusz Myśliwiec: 18 years hands-on with IFS, including IFS Cloud. Based in Kraków, delivering remotely across Europe and globally through an independent practice. You talk to the consultant who does the work, not a sales layer.

IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.

Do planned manufacturing dates match the shop floor?

A review of routing data against the calculation rules shows which time, lot size or overlap value drives the planned date of each part. Manufacturing engineering and planning take part.

Book a routing data review Read about the three lead time types

×
Need Expert Guidance?
We've helped hundreds of businesses succeed. Get a free consultation to discuss your project requirements.
Get Free Consultation
17Years Experience
50Implementations
PRINCE2Certified
100%Success Rate

ROI Calculator

Calculate your return on investment

Input Values

€
€
€

Results

Annual Savings
€ 0
Payback Period
0 months
ROI
0%
Monthly Savings
€ 0

Get Detailed Report

Enter your details to receive a detailed ROI report.