Skip to main contentSkip to footer

IPR Safety Stock Models in IFS Cloud: How Each One Works

How IFS Cloud IPR calculates safety stock: demand models, safety stock models, the cover time limit and a worked example from the documentation.

Independent IFS Cloud practice · Inventory planning design Choose a safety stock model you can explain to the buyer IFS Cloud IPR safety stock is the inventory kept on stock as a buffer to achieve the wanted service level, and the model that calculates it decides how the buffer follows demand. If the model is chosen…

Read more

Handling Units and Packing Instructions in IFS Cloud

How handling units and packing instructions work in IFS Cloud: structure levels, packing from the bottom up, SSCC and labels, and what to set up first.

Independent IFS Cloud practice · Shipping and packing design Design the packing instruction once, so every pallet is described the same way A handling unit in IFS Cloud is a collective name for all types of containers in which parts can be packed, and a handling unit structure describes the packing as done in one or…

Read more

Part Status in IFS Cloud: Onhand, Demand and Supply Flags

What the part status flags do in IFS Cloud: whether a part can hold stock, take demand or be supplied, the default status and the rules for changes.

Independent IFS Cloud practice · Master data design Design the part status set before parts are linked to it An IFS Cloud part status is a master data record that describes the different phases of a part and controls the extent to which the system can use the part. Its parameters cannot be modified once the record is…

Read more

Reservation Rules in IFS Cloud: Which Stock Goes First

How IFS Cloud decides which stock to reserve first: the reservation rules, their order, shipment-assigned quantities, and manual overrides.

Independent IFS Cloud practice · Reservation design Set the reservation rule order to match the stock the warehouse wants to ship first IFS Cloud reservation rules decide which stock record is reserved when several records could cover the same order line. The IFS page on reservation management lists five priority…

Read more

IFS Cloud Ship Goods and Assets: What It Creates

IFS Cloud Ship Goods and Assets creates a shipment order in one company and distribution and internal orders between companies. Limits and set-up.

Independent IFS Cloud practice · Inventory transfer design Know which documents the system creates before you start the move The IFS Cloud Ship Goods and Assets activity starts one move, and the system creates different documents depending on who receives the goods. If the set-up behind each route is not known, a move…

Read more

IFS Cloud Part Availability Control: What Each Setting Does

IFS Cloud part availability control settings: nettable, reservation, issue, movement, scrap, counting and refill, and where the default is set.

Independent IFS Cloud practice · Inventory settings design Know which function reads which parameter before you change an availability control An IFS Cloud part availability control is a small record whose parameters act on different functions at once: planning, reservation, issue, movement, scrapping, counting and…

Read more

IFS Cloud Remote Warehouse: Defaults, Refill, Arrival

IFS Cloud remote warehouse set-up: default availability controls, refill and arrival defaults, and what to decide before stock moves out.

Independent IFS Cloud practice · Warehouse set-up design Decide what remote stock may do before the first part moves out An IFS Cloud remote warehouse holds stock away from the main warehouse, for example at a supplier or in a service van, and it is still stock. If its availability, movement and refill settings stay…

Read more

IFS Cloud Kits and Kit Assembly Orders: How They Work

IFS Cloud kit assembly orders build and change kit serials. Master part rules, kit definition, statuses and what MRP does not plan.

Independent IFS Cloud practice · Inventory design Set up the kit master part correctly, and know what planning leaves to you An IFS Cloud kit assembly order builds or changes a kit serial, which is one stocked unit made of components. Inventory, assembly and planning all touch the kit. If the master part is set up…

Read more

IFS Cloud Warehouse Tasks: Priority and Planning

IFS Cloud warehouse tasks are prioritised by default and operative priority, and planned through workers, groups and a workload view. How to set it up.

Independent IFS Cloud practice · Warehouse planning design Decide which task a worker gets first, before the set-up decides it for you IFS Cloud warehouse tasks are the units of work through which the floor receives picking and transport work when warehousing is used. If task types, workers and priorities are not…

Read more
Abstract illustration on a navy background with the article title: IPR Safety Stock Models in IFS Cloud: How Each One Works

Independent IFS Cloud practice · Inventory planning design

Choose a safety stock model you can explain to the buyer

IFS Cloud IPR safety stock is the inventory kept on stock as a buffer to achieve the wanted service level, and the model that calculates it decides how the buffer follows demand. If the model is chosen without a decision, the buffer cannot be explained to a buyer, or it grows without a limit. The stake is stock held against a service level that nobody chose, or a service level that the buffer does not deliver. This article follows the 26R1 documentation page on IPR safety stock models (titled IPR Time Phased Safety Stock Models), and two 25R2 pages where it says so.

Key takeaways

  • The Demand Model offers Yearly Prediction, History and Forecast, and the Safety Stock Model offers Manual, Time Coverage, Historical uncertainty and Mean Absolute Error.
  • Time Coverage multiplies the forecast per day from the Demand Model by the Safety Stock Cover Time; the page’s example is a yearly demand of 876 and a cover time of 25, which gives a safety stock of 60.
  • Historical uncertainty multiplies the normal inverse of the service rate by the standard deviation of issues in lead time, and Mean Absolute Error takes the deviation from the forecast in Demand Planning.
  • The parameter Max Safety Stock Cover Time, set in the planning hierarchy, limits the safety stock so that it does not get extremely large.
  • IPR can be used on parts with planning method B, and on parts with planning methods A, D, E, F, G and M, where it computes the safety stock only.
  • Period-based safety stock is a separate concept, described on a 25R2 page, and is put on top of regular safety stock only during the defined periods.

1.What does IPR calculate when it calculates safety stock?

The result of the IPR calculation is how much inventory should be kept on stock as a buffer to achieve the wanted service level. The result is written to the Safety Stock field of the inventory part, or to a tab on Inventory Part/Planning Data/General. You can see all the detailed calculations in an Excel sheet, if you access the sheet by right-clicking on the Inventory Part/Planning Data/IPR Parameters tab. The classification of parts and the rule hierarchy of IPR are covered in reorder points in IFS Cloud and are not repeated here.

2.Which demand models can feed the calculation?

The Demand Model has three options. Yearly Prediction simply uses the field Pred Year Cons Qty on the inventory part as the yearly demand for the part. History uses the Lead Time, Cycle Time, No of Issues in Lead Time and the Avg. Qty per Issue to compute the yearly demand. The page gives no further description of the third option, Forecast.

3.Which safety stock models exist, and how does each work?

The Safety Stock Model has four options, and the table gives the formula the page prints for each one.

Model What the page says
Manual Listed as an option; the page gives no calculation for it
Time Coverage Safety Stock = Forecast (day) determined by the Demand Model * Safety Stock Cover Time
Historical uncertainty Safety Stock = NORMINV(Service Rate) * Standard Derivation Issues in Lead Time; the Standard Derivation is computed by the Analyze Demand Derivation background job
Mean Absolute Error Similar to Historical uncertainty, with the important difference that the Standard Derivation is fetched from the forecast in Demand Planning; the printed formula is Safety Stock = NORMINV(Service Rate) * SQRT(MSE in Forecast Period)

The Time Coverage example on the page: with a yearly demand of 876 and a Safety Stock Cover Time of 25, the safety stock is 876 / 365 × 25 = 60.

The Mean Absolute Error model is named for an absolute error, while the formula on the page uses MSE. The 25R2 copy of the page also says MSE: the Standard Derivation is computed from the MSE error for the lead time (plus eventual cycle time) from Demand Planning. This article reports both as printed and does not resolve the difference; confirm in your release which error measure the calculation uses before the model is chosen for a part class.

For Historical uncertainty, the 25R2 page on IPR models describes a wider version than the 26R1 page: Total Standard Derivation = Standard Derivation measured in the lead time + Standard Derivation in the lead time length, where the lead time length Standard Derivation is computed by the Calculate Purchased Lead Time background job. The 26R1 page has one deviation and one job. Name the page you rely on when you document the model. Lead time definitions are covered in lead times in IFS Cloud.

4.What limits the buffer?

There exists a parameter called Max Safety Stock Cover Time, set in the planning hierarchy and used to limit the safety stock so that it does not get extremely large. The page calls this especially useful when using a service level controlled safety stock model, where unnaturally high transactions that are not marked as abnormal result in high safety stocks. The ageing of stock held in a buffer is analysed in the anatomy of stock aging.

5.Which parts can use it?

IPR can be used on parts with planning method B. IPR can also be used for parts with planning methods A, D, E, F, G and M, and it then computes the safety stock only. The page prints the letters without saying what they stand for, so the mapping to your planning methods is checked in the system before the part classes are assigned. Stock that reacts to exceptions is covered in reactive inventory management.

6.What is period-based safety stock, and how does it differ?

The 25R2 page on Time Phased Safety Stock describes a period based safety stock to meet peaks in demand, or periods where lack of capacity occurs. It is put on top of regular safety stock if it is used, but is done only during the periods defined. If the part is handled by MS, the end date of the period must be outside the planning time fence date of the master schedule level 1 part when it is entered. It is not applicable in combination with project MS or project MRP. The 26R1 master scheduling messages page includes the message “Projected balance is below time phased safety stock”, generated when the projected balance falls below the time phased safety stock defined for the period.

The 26R1 page on IPR safety stock models does not describe periods, peaks or capacity gaps. It uses the words “Time Phased Safety Stock” in its title, as the name of the calculation, and for a destination of the result, and describes the models above. The models in this article are therefore not period-based safety stock.

7.Who signs off the service level?

Which number would a buyer quote if asked why a part carries this buffer? The formulas of the service level models contain the service rate, so someone has to set it, and the planner and the buyer agree it per part class. The same people decide the Max Safety Stock Cover Time in the planning hierarchy, because it caps the buffer that the model produces. The planning lead reviews the choice of model per part class, and records which page, 25R2 or 26R1, the documentation of Historical uncertainty relies on. The review interval is a business decision, as the page gives none.

8.How do you test a model before go-live?

Test with one part per model and the same demand history, and write down the expected buffer before each calculation.

Scenario Expected buffer Owner
Time Coverage, yearly demand 876, cover time 25 60, as 876 / 365 × 25 (the page’s example) Planner
Manual Record the buffer; the page gives no calculation Planner
Historical uncertainty NORMINV(Service Rate) * Standard Derivation Issues in Lead Time; record the result of the Analyze Demand Derivation job first Planner
Mean Absolute Error NORMINV(Service Rate) * SQRT(MSE in Forecast Period); record which error measure the release uses Planner
Model that produces a very large buffer, with Max Safety Stock Cover Time set Buffer limited by the cover time parameter; record both values Planning lead
Part with planning method B and part with planning method A IPR available on B; on A it computes the safety stock only Planning lead

9.What does a safety stock model checklist contain?

The safety stock set-up is ready for go-live when each check below has a record behind it.

  1. The demand model and the safety stock model are decided per part class.
  2. The service level behind each service-level model is signed off by planning and purchasing.
  3. Max Safety Stock Cover Time is set in the planning hierarchy.
  4. The planning methods of the parts are checked against the methods the page lists.
  5. The choice for Mean Absolute Error and Historical uncertainty names the documentation page it relies on.
  6. The six test scenarios are recorded with evidence.

10.Frequently asked questions

How does IFS Cloud IPR calculate safety stock?

The IFS Cloud IPR calculation returns how much inventory should be kept on stock as a buffer to achieve the wanted service level. The Demand Model offers Yearly Prediction, History and Forecast, and the Safety Stock Model offers Manual, Time Coverage, Historical uncertainty and Mean Absolute Error.

What is the difference between the Historical Uncertainty and Time Coverage models?

In IFS Cloud IPR, Time Coverage calculates the safety stock as the forecast per day determined by the Demand Model multiplied by the Safety Stock Cover Time. Historical uncertainty calculates it as NORMINV of the service rate multiplied by the standard deviation of issues in lead time, which the Analyze Demand Derivation background job computes.

What does the Max Safety Stock Cover Time limit do?

Max Safety Stock Cover Time is a parameter set in the IFS Cloud planning hierarchy that limits the safety stock so that it does not get extremely large. The documentation calls it especially useful with a service level controlled model, where unnaturally high transactions not marked as abnormal result in high safety stocks.

Which planning methods can use IPR for safety stock?

IPR in IFS Cloud can be used on parts with planning method B. It can also be used for parts with planning methods A, D, E, F, G and M, and it then computes the safety stock only.

What is time phased safety stock?

Time phased safety stock in IFS Cloud is a period based safety stock to meet peaks in demand, or periods where lack of capacity occurs. It is put on top of regular safety stock if it is used, but is done only during the periods defined.

11.About the author

Dariusz Myśliwiec: 18 years hands-on with IFS, including IFS Cloud. Based in Kraków, delivering remotely across Europe and globally through an independent practice. You talk to the consultant who does the work, not a sales layer.

IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.

Can you explain your safety stock numbers to the buyer?

A review of the safety stock models by part class, with the planner and the buyer, shows which model and which service level sit behind each buffer.

Book a safety stock review Read about reorder points

×
Need Expert Guidance?
We've helped hundreds of businesses succeed. Get a free consultation to discuss your project requirements.
Get Free Consultation
17Years Experience
50Implementations
PRINCE2Certified
100%Success Rate

ROI Calculator

Calculate your return on investment

Input Values

€
€
€

Results

Annual Savings
€ 0
Payback Period
0 months
ROI
0%
Monthly Savings
€ 0

Get Detailed Report

Enter your details to receive a detailed ROI report.