IFS Applications 10 Extended Support: what has to exist by 27 March 2027
According to the published summaries of the IFS terms, Apps 10 Extended Support runs through 27 March 2027 by default for customers who have purchased IFS Cloud and are upgrading, and those customers with an active IFS Cloud upgrade and migration plan may extend it through 27 March 2028. From 15 October 2026 the first date is about 23 weeks away, which is shorter than the 6 to 12 months IFS quotes for a migration, so what has to exist by then is a documented plan and not a go-live. Confirm every date below against your own contract and with your IFS account team in writing. Any other Apps 10 customer should ask IFS for their position in writing.
Key takeaways
- Standard Support for Apps 10 ended on 27 March 2025. Default Extended Support runs up to two years, through 27 March 2027, for customers who have purchased IFS Cloud and are upgrading.
- Customers with an active upgrade and migration plan may extend Extended Support through 27 March 2028, subject to the applicable terms. That date is the scheduled end of Extended Support under current terms for those customers.
- Customers who still need support after 27 March 2027 without an active plan need a new Order Form.
- The published summaries of the terms do not define "active plan". Ask IFS for the definition in writing before you build the plan document.
1.Which three dates matter, and what do you need on each one?
Three dates frame the Apps 10 support position, and they sit on one timeline. The dates come from the IFS Extended Support Terms as summarised in public commentary of October 2026. I have not seen the contract wording for your site, so check this section against your contract and ask your IFS account team to confirm each date in writing.
| Date | What happens | What you need on that day |
|---|---|---|
| 27 March 2025 | Standard Support for Apps 10 ended. | Nothing new. This date explains why you are now in Extended Support, which IFS describes as subject to additional terms and fees. |
| 27 March 2027 | Default Extended Support ends. It runs up to two years for customers who have purchased IFS Cloud and are upgrading. | An active IFS Cloud upgrade and migration plan as IFS defines it (ask for the definition in writing), or a new Order Form for support beyond this date. |
| 27 March 2028 | Scheduled end of Extended Support under current terms, for customers with an active plan, subject to the applicable terms. | Live on IFS Cloud, or a written answer from IFS about what support exists after this date. |
The three dates give each customer who has purchased IFS Cloud and is upgrading one of two positions on 27 March 2027. Either you hold an active plan and may extend to 27 March 2028, or you hold a new Order Form for support beyond the default date. A customer with neither has no documented support position after 27 March 2027, and that is the situation this article helps you avoid. Any other Apps 10 customer should ask IFS for their own position in writing.
2.What does an "active plan" mean, and why ask IFS for the definition?
The published summaries of the terms do not define "active IFS Cloud upgrade and migration plan", so anything I write about its content is a question to ask and not a fact. The date 27 March 2028 depends on that phrase, and a phrase without a definition is a contract risk for the finance sponsor.
These are the questions I would put to the IFS account team. Ask for the answers in an email you can file with the contract:
- Form of the plan. Is it a document, a signed project plan, a statement of work with a start date, or an executed IFS Cloud order?
- Evidence of activity. Does IFS expect milestones to be met, and who confirms that the plan is still active?
- Timing of acceptance. Must the plan exist before 27 March 2027, and who at IFS accepts it?
- Loss of status. What happens to the extension if a milestone slips or the scope changes?
- Cost. What additional terms and fees apply to Extended Support at each stage, in euros or your contract currency?
- Interaction with the order. Which IFS Cloud order or subscription must be signed before the plan counts, and from which date does the subscription term run?
- Go-live and support. Does go-live on IFS Cloud change your Extended Support position, and from which date does the change apply?
- Order Form. If the plan is not accepted, what does a new Order Form for support after 27 March 2027 contain, and what is its term?
If the account team does not reply within a week, send the same questions again, copy your contract manager and keep the thread with the contract file. Question 7 covers a situation the summaries do not address, and question 8 one they describe only in outline, so they are the ones I would not leave to a phone call. For the wider decision between upgrade approaches, see strategies in ERP upgrade planning.
3.What does the calendar look like when you count backwards?
From 15 October 2026 to 27 March 2027 is 5 months and 12 days, or 163 days, which is about 23 weeks. To 27 March 2028 it is about 17 months. IFS says migrations typically take 6 to 12 months. The time left to the 2027 date is therefore already shorter than the low end of IFS's own range.
The table below is plain calendar arithmetic, offered as an illustration. Your project's duration comes from your own plan. The table assumes go-live happens at the end of the stated duration with no overrun, and the 2028 column assumes the extension is granted.
| Start date | Duration | Go-live | Against 27 March 2027 | Against 27 March 2028 |
|---|---|---|---|---|
| 15 October 2026 | 6 months | 15 April 2027 | 19 days after | Before, 11 months and 12 days of margin |
| 9 months | 15 July 2027 | After | Before, 8 months and 12 days of margin | |
| 12 months | 15 October 2027 | After | Before, 5 months and 12 days of margin | |
| 1 January 2027 | 6 months | 1 July 2027 | After | Before, about 9 months of margin |
| 9 months | 1 October 2027 | After | Before, about 6 months of margin | |
| 12 months | 1 January 2028 | After | Before, 86 days (about 12 weeks) of margin | |
| 1 September 2027 | 6 months | 1 March 2028 | After | Before, 26 days of margin |
| 9 months | 1 June 2028 | After | After | |
| 12 months | 1 September 2028 | After | After |
Two readings follow from the table. Every row ends after 27 March 2027, including the fastest one, so every project needs either the plan-based extension or a new Order Form. And the 2028 date leaves real room only for a project that starts by early 2027.
The September 2027 start is the case I would not accept. It leaves a 6-month project with 26 days of margin and anything longer with none, and it relies on a plan IFS has not defined in writing. Whatever the duration, the go-live has to land in a cutover window your business can tolerate, so check the date against your financial period close. Why ERP upgrades fail lists the planning gaps that sink projects in this phase, and being prepared for an ERP upgrade covers the sponsor-side preparation.
4.What should you do in the next 30 days?
The first 30 days after reading the dates are best spent on a written position with IFS and a named budget owner. The schedule below is the author's practice and uses dates from today, 15 October 2026.
- By 22 October 2026: find the Apps 10 support and subscription clauses in your contract and note the term end date and any renewal date.
- By 29 October 2026: send the eight questions about the active plan to your IFS account team in one email.
- By 5 November 2026: name the budget owner for the upgrade. The extension decision needs a budget owner and not only a project lead, because the answers to the cost questions change the budget.
- By 13 November 2026: count your customisations and integrations, choose a start month and write down the matching go-live date. The counts feed the duration estimate, and the rows of the countdown table are the model for the dates.
With these four items done you can judge whether an extension to 27 March 2028 is realistic or whether a new Order Form is the safer route.
5.What should the plan document cover before 27 March 2027?
A plan document that can carry a support extension names an owner, a budget and dated phases for every workstream of the move to IFS Cloud. This list is the author's practice from upgrade projects, and it may differ from what IFS accepts as an active plan.
| Workstream | What the document states | Evidence you can attach |
|---|---|---|
| Customisations | Each customisation with a decision: retire, rebuild with a supported extension mechanism, or replace with standard configuration. | An inventory with an owner and a decision per line. |
| Integrations | Each interface with its owner, direction, frequency and the system on the other side, and which ones need a new design. | An interface list agreed with the owners of the connected systems. |
| Data migration | Which data moves, which is archived, and who signs off on data quality. | A migration scope statement and a sign-off owner. |
| Process validation | The business processes that must be proven on IFS Cloud and the person who proves each one. | A process list with a named validator per process. |
| Test and cutover | Test cycles, the cutover weekend and the fallback decision point. | A calendar checked against the financial period close. |
| Governance | One accountable executive, a budget line and an approval date. | A signed budget approval and a steering group list. |
The data migration row deserves its own planning, and the articles on the IFS Cloud data migration plan and IFS DMM step by step go into the mechanics. Assign each process in the validation row an owner by name before the document goes to IFS. The IFS Cloud upgrade readiness checklist on ifs-erp.com turns these workstreams into questions you can score. If you want the plan reviewed or written with you, I do that work as part of IFS Cloud services.
6.What are you upgrading to?
The destination is IFS Cloud, which receives updates continuously, as service update vs release update explains, so in my reading the move also changes how you take updates after go-live. The cost of that change depends on how you tailor the system. Tailoring through supported extension mechanisms keeps your changes outside the standard code, which is the idea described in the clean core.
That choice belongs in the plan document, because each customisation you rebuild now is a change you will test again at every update. For a project with a data-heavy scope, professional data migration services cover the migration work on its own. The implementation documentation kit offers templates for the update strategy and the handover, and the SCM Automation Pack adds purchasing exception monitoring after go-live, with nothing installed in your IFS Cloud.
7.Frequently asked questions
When do I need a new Order Form for IFS Applications 10 support?
According to the published summaries of the IFS Extended Support Terms, a customer who still needs Apps 10 support after 27 March 2027 and has no active IFS Cloud upgrade and migration plan needs a new Order Form. Confirm the wording against your own contract and with your IFS account team in writing.
Does the 27 March 2028 date apply to every IFS Applications 10 customer?
No. According to the published summaries of the terms, 27 March 2028 is the scheduled end of Extended Support for customers with an active IFS Cloud upgrade and migration plan who extend, subject to the applicable terms. Customers who have purchased IFS Cloud and are upgrading, but have no such plan, have the default end date of 27 March 2027; any other Apps 10 customer should ask IFS for their position in writing.
Can we stay on IFS Applications 10 after Extended Support ends?
The published summaries of the terms name 27 March 2028 as the scheduled end of Extended Support and describe no support after it. Ask your IFS account team in writing what support exists for Apps 10 after that date and on which terms, and decide on that answer.
How long does a migration from IFS Applications 10 to IFS Cloud take?
IFS says migrations typically take 6 to 12 months on its public customer success page. Your own figure comes from the plan document: the number of customisations and integrations, the data to migrate and the test and cutover windows you can schedule.
Who pays for IFS Applications 10 Extended Support?
The IFS customer success page says Apps 10 is in Extended Support "subject to additional terms and fees", and that customers can access Apps 10 Extended Support at no extra cost when signing up to IFS Cloud. The fee for your site depends on your contract, so ask IFS for the figure in writing.
8.About the author
Dariusz Myśliwiec brings 18 years of hands-on work with IFS (Apps 7.5–10 and IFS Cloud). IFS Certified Associate Consultant. PRINCE2® 7. Based in Kraków, delivering remotely across Europe and globally as an independent practice, so you talk to the consultant who builds it.
Selected clients: Fugro · LGC · BVI Medical · Betafence (PRÆSIDIAD) · Barlinek · NGK Ceramics · Newag · Oleofarm.
Source for the IFS statements on fees, access and migration time: IFS customer success page, read on 15 October 2026. The support dates come from published summaries of the terms and are not legal advice. IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.
Get the IFS Cloud upgrade plan on paper before 27 March 2027
Send me your start date and your customisation and integration counts. On a 30-minute fit call we can check them against the 27 March 2027 and 27 March 2028 dates and agree what the plan document needs, from readiness through data migration to implementation.